Backland Eco House Development
Springfield Road, Brighton
One of our long standing developer clients in Brighton & Hove, who owns this Brighton site had a history of failed planning applications by others.
We were engaged in 2018 to develop designs for a dwelling on part of the garden to the rear of an HMO property they own.
After a positive pre-app, we submitted plans for a single storey, two bedroom detached house and gained consent at delegated powers.
We were then engaged to develop the working drawings package, with the project being built out in 8 months.
The house comprises vertical cedar cladding and a sedum roof. It is constructed from a SIPS panel system and uses an air source heat pump, with a close to zero carbon eco rating.
We have a great track record on delivering consents on tight, backland sites in Brighton & Hove and other parts of Sussex, where others have failed - get in touch if you have a similar site and need a fresh look.
Address
Springfield Road, Brighton
—
Scope of Works
RIBA Stages 0-4
—
Contractor
We Build Ltd
—
Design Length
Stage 0-3 - 4 months, Stage 4 - 2 months
—
Build Time
8 months